Project Almeria

Pricing opinion generated from uploaded project teaser. All figures are deterministic model outputs.

TechnologyGround-mount Solar PV
Capacity62 MWp
LocationAlmeria, Spain
CODQ2 2024
RevenuePPA + Merchant

Maximum Bid Price

Within comp range
Maximum Bid Price
820
EUR k / MWp
Total: EUR 50.8M
Project IRR at bid9.2%
Equity IRR at bid15.3%
EIRR ex-BESS at bid14.8%
Target PIRR9.0%
Target EIRR15.0%
Min EIRR floor10.5%
Binding constraintPIRR floor (9.0%)
Comp medianEUR 850k/MWp

Yield Curve Analysis

6 price points
Price (EUR k/MWp)Total (EUR M)PIRREIRREIRR ex-BESSBinding
70043.410.8%18.4%17.6%-
75046.510.1%17.0%16.3%-
80049.69.5%15.8%15.2%-
820 ← Bid50.89.2%15.3%14.8%PIRR
85052.78.8%14.7%14.2%Below target
90055.88.2%13.5%13.1%Below target

Comparable Transactions

5 matches
TransactionCountryTechnologyMWpPrice (EUR k/MWp)Date
Andalusia Solar ISpainSolar PV75850Q1 2024
Murcia GroundSpainSolar PV45810Q4 2023
Valencia Solar ParkSpainSolar PV90880Q3 2023
Algarve PVPortugalSolar PV55790Q2 2024
Extremadura SolarSpainSolar PV110830Q1 2024
Comp RangeEUR 790 - 880k/MWp
MedianEUR 830k/MWp
Bid vs Median-1.2%

Risk Assessment

3 flags identified
Merchant Revenue Exposure
Approximately 35% of projected revenue is exposed to merchant electricity prices beyond the PPA term. Price forecasts assume a 2% annual real decline, but actual merchant pool outcomes in Iberia have shown higher volatility. Sensitivity: +/-50 bps PIRR per 10% merchant price movement.
Medium
Grid Curtailment Risk
Almeria substation shows 87% capacity utilization on the relevant network node. While no curtailment has been reported to date, new generation capacity in the pipeline (240 MW permitted, 180 MW under construction) could trigger curtailment events within the hold period.
Medium
Module Degradation Assumptions
Teaser assumes 0.45% annual degradation. This is within the standard range for Tier 1 monocrystalline modules (0.40% - 0.55%). No adjustment required at this assumption level.
Low

Recommendation

Proceed with Conditions

Conditions for proceeding at EUR 820k/MWp

  • Obtain independent grid capacity assessment from the TSO or a qualified grid consultant to validate curtailment risk before final bid submission
  • Structure merchant revenue hedge or floor mechanism for the post-PPA period, targeting minimum 60% revenue certainty
  • Request updated module degradation warranty from the EPC contractor, ensuring alignment with the 0.45% assumption used in pricing
  • RTB Score of 74/100 supports proceeding. Bid is 1.2% below comp median, providing limited but adequate margin against comparable transactions